Showing posts with label 2009 construction. Show all posts
Showing posts with label 2009 construction. Show all posts

Saturday, May 15, 2010

Not your goal after $47+k

This is what the cabin looked like when the appraiser came out last fall during Deer Hunting Season Shut Down when the cabin was supposed to be completed. I used the one photo to show that the cabin was not insulated and drywalled but did not show that the drywall was on the ceiling and used the same photo you've already seen of the ceiling as it was hanging over the appraisers head that fateful day in November. That will forever go down as a top ten embarrassing moment in my life. Below is the what was paid to Dudenas Contracting at the time of the photos. We were later billed another week's work for the labor for the drywall installation. A three man crew took a week and it was roughly $2,640 plus materials. So at this point, a month was spent building the pole barn (billed separately and not included in these figures) and four and a half months was spent on the cabin. After Deer Hunting, another week and another approximate $2,640 plus materials was spent on siding the cabin. With the siding on, The Secret Cabin was now ready for the Winter weather which was moving in when I had Dudenas remove all their equipment from our property. To avoid ugliness, I didn't say much past, we need all this picked up so I don't run it over with the tractor and snow thrower; no, lumber goes in the barn not in the basement of the cabin; no, don't leave that - you need to take ALL your equipment because come Spring, if I don't need it, it gets recycled; I don't know, I just want to see my husband, I'm exhausted; I don't know, I'm completely fried; I don't know, I haven't seen my husband in five months. While I was thanking God/Goddess and all spiritual entities of light, love, and goodness than somehow I got the cabin to the point where it was ready to brave the weather, under my breath I was screaming, "get your shit and your asses off my property NOW so I can throw myself face down in the snow and cry so hard that I can't hear my heart crack and my soul moan." I stood there looking at the cabin seeing what I didn't get done. What I FAILED to get done. I fought tooth and nail to get the cabin to the point it was at but it was no where what should have been done. Dealing with these guys really ran me through the wringer. Worse, every time I tried to get issues addressed, I was personally verbally assaulted by Mark. I only left the job site once during the day to go cry my eyes out and I only cried myself to sleep once. I only threw (not physically) one guy from Dudenas' crew off the job. I only fired one other contractor because he gave me crap about a job he did incorrectly - set in concrete I might add. I did NOT pick up a 2 x 4 and knock some respect into any man for all of woman-kind everywhere and as a result stayed a free member of society. Our wallet took a beating too. Remember the bill to remedy some of the seriously ugly craftsmanship that went on is not yet in but is an additional expense to this phase of the project which will far exceed the last $2000 we are refusing to GIVE to Mark. I have consulted a few industry experts and all agreed that the cabin should have been completed for the amount of money we paid for the time that had passed. 
32 x 24 Lower level (basement addition) 20,385

Extremely slow labor and wasteful use of materials:
Enclosed and improved front porch (adds 8 x 24 of conditioned space)
Removed two walls and loft floor; added 8' to remaining, existing loft
Structural reinforcement and improvements
Soffits, facia, and trim along bottom of cabin
New roof, install chimneys
Removing old widows, reframing for new windows and doors, and
Installation of 1st shipment of windows and doors
Job site cleaning (man's definition of clean) 21,407.49
          Plus above mentioned work (ceiling and siding)                              5,280

          Total                                                                                                        47,072.49





Friday, May 14, 2010

Business as usual

As of yesterday, we have officially contested our ex-contractor's final bill. We completely audited the entire job. A task that took us two months. That's what happens when you don't get the requested backup paperwork or a complete detailed bill. It wasn't until the next to last bill that our request for backup paperwork was provided. We did find material bills that we were charged for that weren't ours and deducted them. There was also a credit for materials that we didn't receive credit for. We did not answer the ex-contractor's phone calls because the "botches" were still being dealt with and we knew there'd be a fight. We have a list of extra work performed by my new crew to fix these botches. I can hear the calculator running in the background as I type this. While, the final dollar amount is not in yet, we received another invoice in the mail from the ex. We knew that telling the ex-contractor that we had already generously compensated him for the quality and amount of work they did in the time frame they did it in was going to unleash major ugliness. Once again, I tried to make the point that the work performed was not done so in a timely fashion. It does not take a crew of four guys four weeks to build a simple, basic 30 x 60 pole barn. If it took them two to three weeks longer than it should have for just the barn project, how much time did they dawdle away while the time and material meter was running on the cabin? Well, just in case you are wondering, the answer to that question according to Mark Dudenas, Dudenas Contracting, Calumet, Michigan; is that it doesn't matter. Which then, as it has happened on several occasions, I was personally, verbally assaulted. After all, it is easier to bully someone than it is to be responsible for the work performed. Apparently, my big, scary 5 foot 4 and 3/4, looming, all powerful, womanly badassness yelled at EVERY poor, innocent, quaking in their steel toed boots workmen on the job and got along with NO one and Mark Dudenas has people that will back him up on that. Seriously, I want to see one of these poor, helpless 6' tall guys point at me and tell everyone how mean I was to them when I bought them muffins, cookies, and/or beer. I realize that I am not perfect however, usually, I repeated myself at least six times before I got frustrated enough to start stringing colorful metaphors together at higher decibel levels. I was able to put up with watching the guys trip over all the construction waste and my requests for them to clean things ignored for at least two to three weeks before I threw everything out the front of the cabin myself. The real clincher here is that I don't know how Mark could really know anything about our job as he wasn't doing his job and managing it. He maybe showed up for 15 minutes a day, three to four times a week. So, once again, as usual, my questions were met with hostility, bullying, and verbal assaults and accusations. And here I thought I was the customer, the one, in this case, NOT signing the paychecks. When I pointed out that I did get along with other contractors. He accused them of not doing their jobs. Whatever agreements I had with other contractors were between me and that contractor, of which the details were not anyone else's business. On the telephone with Mark, I was too busy having my personality attacked to even get out that we were not paying the bill because we felt we already paid him more than enough and that we weren't happy customers. When he talked to my husband, because he refused to talk to me after he hung up on me and I called him back, my husband was able to tell him that we felt we paid him more than enough already and that we were using the money he invoiced us to pay for work to correct their work. Of course, he was insulted and wanted a for instance. The Man was able to get out item number one when Mark started up again. The Man was not verbally assaulted, but, of course, no conversation with a contractor that doesn't do his job yet feels he still should be paid is complete without the threat of being sued. So, we stated our case in an email, suitable for forwarding to his attorney (our contact information was included along with instructions to please send all correspondence to both of us). Now, back in the day, yours truly here worked for a couple of attorneys. I love attorneys. They are articulate and logical. My grammar and communications skills were never sharper than when I worked for them. I don't know if Mark will take the email we sent in to his attorney or not. However, knowing and loving attorneys as I do, he will take one look at that email and tell Mark that he should be thankful we don't sue the pants off him and that the pittance compared to the rest of the job and what we've already paid is not worth his time. I also know that in the meantime, before Mark can get to his attorney, yours truly is not under any kind of gag or cease and desist order. So let's have a little bit of sick, twisted fun here, shall we? I am going to post the cost of damages to us right here on the blogosphere. Gross, gory details straight from the source and motivation for all about to build or repair to be very, very careful. Stay tuned. Again, hell hath no fury like a woman scorned or screwed over by one of the contractors that give the others a bad name.

Wednesday, December 9, 2009

Fried Wifi Brain


Cripes. Mike and I are super exhausted. We've seen each other for four days in the last five months. It is Winter in the Keweenaw. So, while we had planned on having the cabin done by the last week of October (our very latest, back up deadline if we didn't make the other deadlines) so we could move in, here it is December with lots of snow so we called it quits for the year. I am going to refer to this part of the cabin remodel as Faze I - Rough in with emphasis on the word "rough" and declare this phase over. I leave the Keweenaw this Saturday and fly back to Ohio. Mike will come up to the cabin the week of Christmas and finish hooking up the solar system. Our plan is that he'll be back in time for Christmas Eve. Then, Mike and I are going to take a little break from the construction stuff and start back up when we feel ready. The contractor that we had working on the cabin this year is all cleared off our property and it's a big relief. We are talking to another contractor for the finish work.

Tuesday, November 17, 2009

Getting a little on the side

Ya know, I find myself saying things that are weird to say about this whole construction drama. So, things are NOT working out with my current contractor and I want to toss him out and fire his ass. It's so reminiscent of a bad relationship break up only he never bought me a ring to throw at him as I stomp indignantly off into the sunset. It's hunting season. This current contractor's usual level of lack of customer service has left me alone for two weeks without any workers or any work being done. What's a girl to do to fill her lonely, quiet, construction worker-less days? Not let the job site get cold. That's for darn sure. The last shipment of Loewen Windows came in along with a couple of guys to install them. So, yes, guilty. I'm guilty of cheating on my contractor with another contractor. So, these new guys are amazing. We stopped work and went into town for lunch. We went our separate ways for lunch and I was took my sweet old time as I usually do with my other crew. I had lunch. Set my fork down between bites. Chewed slowly and thoroughly actually tasting my food. Then I ran some errands. Then I drove within the speed limit. Good thing the old ticker is still a work horse. I'm still suffering from a little disbelief though. Eric and Jake were done installing the windows. As if that weren't shocking enough, they were, get this, cleaning up. Then Eric said, in slow motion with the camera in tight on a shot of his lips, "Is there anything else you would like us to do for you while we're here?" After, visions of laying on the ground and getting the electric paddle treatment to the chest cleared my head, I responded with an intelligent, "Uh, no?" After as much a recovery as anyone in my shoes could make, I was able to point at the cabin and kind of stutter, "Come back to UP? Proposal to finish cabin?" while refraining from throwing myself down on the ground and holding them by the ankles and crying, "Don't leave me; finish my cabin, please." So, I'm getting a proposal. And so, yes, I'm guilty of courting another contractor on the side while I'm still hooked up with this current contractor. My new contractor has a cooler truck too! Na, na, so there.

Friday, October 16, 2009

Fall y'all





First, a quick word on the weather from UP North: Wa! (local saying meaning "wow"). For the rest of us, the word ugly will do the trick. Lots of cold, wind, rain, sleet, and snow. Even people who have been here a while are saying it's unseasonably cold right now and that it's pretty unusual to see color on the trees and snow on the ground.

I am flying to Ohio today so that I can take care of the animals while Mike comes UP here and installs the solar panels. Since my last update, the electrician has wired the cabin and I have been working on the plumbing. Yep, I can "sweat pipe" meaning solder. I also know how to glue together the black ABS piping too. I do have an experienced guy who is the brains and the brawn of the operation but technically because I, the owner, pulled the permit means I, the owner, have to do the work. I did that because we were getting ridiculously high estimates for the plumbing and the plumber I hired already had one part of the job wrong and had a mouth I didn't want to listen to so I wasn't going to torture myself or anybody else and ended that immediately.

The guys started the barn last week, are working on it this week, and will probably be working on it again next week. Geez. Then we're back in the cabin for insulation and drywall with a two week break for hunting season. Apparently, they shut the UP down and go hunting. After, that it's December. Yep, December. We should have our last shipment of windows waiting for us (they come in opening day of hunting season) and we'll get them installed and that will be it for the year.

Sunday, October 4, 2009

The world's cutest kitchen window

Well, we ran out of that beautiful weather we were so lucky to have for so long. It has been gray and raining and a bit chilly for just about two weeks now. Fall is here. The boiler is down in the apartment building so there is no heat. I'm waiting for a chimney part to come in for the cabin so there is no heat there either. We have made progress in the cabin though! I fired the plumber so I will be doing the plumbing. I found an expert helper though. The building inspector is coming out on Monday. The carpenters will be out building the barn this week while I do plumbing and the electrician wires the cabin. Hopefully, the chimney part will come in and then we'll be insulating and hanging drywall in the cabin. We're coming down the home stretch now! Mike and I will switch places in a couple of weeks. He'll come here and put up the solar array and I'll go to the Ohio farm and take care of the critters and pack. I have to take some pictures yet with the windows in.

Tuesday, August 11, 2009

Hollywood Hell Week


Except not in Hollywood and no future singing sensations. Where is Simon Cowell when you need him? I'm on week 2 at the cabin. Last week was ugly. Job foreman would NOT listen, gave me a lot of grief, and was just plain snark-y. I blew up and swore like a sailor. It didn't work. Unless, I was going for high blood pressure readings. When things weren't ready for the heater mason, I called the construction company owner and told him things weren't going well. Didn't get much response so I brought in a couple of guys to help me. Nope, not to proud to pick men up off the street. When owner got there yesterday morning, I let him know he lost the additional work we have and that he'd have to earn the next stage of the job. He said that wasn't fair. I told him that he'd learn to take me seriously and that's the way it was going to go. So going for the wallet worked and I got more guys and everyone got the lead out and busted butt and the job got caught up. So, I'm thinking positively now and expect things to go well. Here's a little sneak peak at the lower level heater. This is after like 5 hours of work - and they had to set up all their stuff including shoveling dirt to be able to get into the basement and move all their block by hand because I couldn't get the job foreman to do it.

Thursday, July 23, 2009